- Budget: ~RMB 00,000
- Products: Pulse Electronic Fence
- Construction: Antongruida
Electronic Fence case at a substation in Wanzhou District, Chongqing. The site is trapezoidal in shape, the fence structure is a cement wall with a marble structure on top. Antongruida dispatched 6 on-site Electronic Fence construction workers; the construction period was about 7 days, the result was good and was recognized by the user, once again verifying our company's cooperation with China Southern Power Grid. About 1,200 meters were constructed, divided into 10 Electronic Fence zones, using Antongruida Pulse Electronic Fence products, 6-wire installation at a height of 80CM, managed via a Pulse Electronic Fence control keypad.





- Previous: Electronic Fence Case at a New Industrial Park in Boluo, Huizhou
- Next: Electronic Fence Case at a Substation in Liangshan, Sichuan
Please contact us right away or call the hotline: +86-13590284141. We will answer all your questions in detail. Project Manager Online