- Budget: ~RMB 00,000
- Products: Pulse Electronic Fence
- Construction: Antongruida
The Nixi 110KV Substation in Xingyi, Qianxinan, Guizhou: the site is trapezoidal, with a cement wall whose top is marble.
Construction is about 600 meters, divided into 6 electronic fence zones, using Antongruida Pulse Electronic Fence products, 6-wire installation, height 80cm, managed and controlled by an AT-KP32 control keypad.
4 on-site workers, construction period about 6 days; the completion effect was good and recognized by the user, once again verifying our company's cooperation with China Southern Power Grid.
For more electronic fence installation needs, please call our company's technical staff: 13590284141, Engineer He.